  Aarsleff scores at Warsaw`s new national stadium  
 


Project Profile – Warsaw Stadium

 

The ability of the leading Danish civil engineering contractor Per Aarsleff and its European subsidiaries to pool and combine their expertise and resources, provides the flexibility to bid for and successfully execute huge projects, which could otherwise be outside the normal capability of the group’s individual companies. A prime example of this advantageous facility is the recent successful completion, ahead of programme, of the mega precast concrete piling contract in Poland’s capital Warsaw for the new National Stadium being built for the 2012 European football championships, which will be jointly held in Poland and neighbouring Ukraine.

Per Aarsleff’s Polish subsidiary Aarsleff has to supply and install around 9,000 large section, heavily reinforced precast concrete piles in just five months. These will provide the bulk of the foundation for the 55,000-seat stadium’s multilevel terraced seating and main support stanchions for the roof, with its retractable inner membrane over the playing surface. “We are the largest precast concrete pile manufacturer and contractor in Poland and could have completed this prestigious contract without the support of the other subsidiaries,” says Aarsleff managing director Przemyslaw Nowak. “However, this would have been to the detriment of our other clients in Poland while we were engaged in this huge contract for the National Stadium. So we decided to allocate some of our rigs to our other smaller domestic projects and supplement the stadium contract with larger rigs, operators and piles from the parent company and other subsidiaries. We were able to mobilise very quickly and the combination of resources, rapidly pooled together with our established core operation and organisation in Poland, was the key to our success here.” 

The National Stadium, designed by J.S.K. Architekci Sp. based in Warsaw, in conjunction with gmp-Architekten von Gerkan, Marg und Partner from Berlin, and civil and structural consulting engineer Schlaich Bergermann und Partner from Stuttgart, is being built directly in the basin of the existing 10th Anniversary Stadium. The original stadium, on the east bank of the River Wisla, opened in 1955 and was built on the rubble from Warsaw devastated and destroyed by Nazi Germany in the Second World War.

The new stadium will have 72 backward raking stanchions around its perimeter to support the fixed roof over the seating and integral folding and retractable membrane over the pitch. There will be nine levels in the arena, including a five level concourse under the terraced seating for offices, conference facilities and restaurants, a further two lower levels for players’ changing rooms and press and two levels directly under the pitch’s playing surface for underground parking for about 1,700 cars. The stadium is estimated to cost between PLN1.5 to 2.2billion (€335 to €490M) and is scheduled for completion at the end of 2011, ready to stage the opening game, group matches and quarter and semi finals of the Euro 2012 competition.


Due to the potentially difficult piling in the compacted backfill, the stadium’s design team instigated and paid for a comprehensive pile testing regime to determine the suitability of different types of piling and to help avoid potential problems during the main piling works. Aarsleff, together with a handful of other companies, took part in an extensive programme of test piling in May 2008. The various techniques were assessed by a separate team of independent foundation specialists, who recommended to the design team that 400mm square section precast concrete piling should provide the vast bulk of the stadium’s foundations. This method was supplemented with some large diameter bored piling for the main stanchions and hundreds of stone columns installed directly under the playing area.

The independent foundations specialists’ recommendations where accepted by the stadium client National Centre of Sport and the Warsaw based main earthworks and substructure contractor Pol-Aqua. The company needed to check that Aarsleff could make and supply the required vast numbers of precast piles fast enough and install them in the very tight programme. Aarsleff was successful with its tender and Pol-Aqua awarded the company an approximate PLN42M (€9M) subcontract to supply and install around 9,000 of its 400mm square section piles. All piles were between 6m to 26m long and contained considerable additional reinforcing specified by the stadium’s design team and needed to take the required design loads.

Aarsleff moved very quickly and gathered together its core national team of heavy-duty rigs, operators and Polish engineers, supplemented with resources from the parent company in Denmark and its various subsidiaries. “For the stadium project we needed the group’s bigger rigs with the heavier hammers to cope with the heavy and big section piles,” says Per Aarsleff foundation works group manager Lars Rande. “In addition to the big Polish rigs we brought in two each from Germany, UK and Denmark, plus operators. We also combined and used our joint pile manufacturing capacity from our KPB pile factory in Poland and Centrum Pæle in Denmark. The KPB plant at Kutno, 120km west of Warsaw, did not have the capability to supply all the piles for the stadium and other projects in Poland at the same time so we imported about 20,000m from Denmark. We also brought over our chief mechanic from Denmark, but relied on all Polish engineers and project leader, as they know the language and how to deal with local issues.”

Aarsleff started onsite at the end of October 2008 and moved rapidly to build up the site team and rigs and create a large stock of piles on site. Piles were only allowed to be brought in at night due to local daytime traffic restrictions, as the fleet of lorries needed to transport them would have considerably added to the already congested road network in Warsaw. Aarsleff assembled a fleet of up to nine heavy-duty rigs at peak production and included two Banut 850s, a Hitachi KH125 and KH180, three Junttan PM20s and two Junttan PM25s, and all fitted with 7t to 9t hammers. Working 16h/day in two equal shifts, six days a week, the site team split the project up into 29 separate areas, each basically operating like an individual contract. Each sector was enclosed in a steel sheet piled cofferdam previously installed by Pol-Aqua.  The main contractor bought and drove an estimated 30,000m2 of sheet piling using a range of piling equipment hired in from all over Poland.

The old arena embankment’s inner sloping face was peppered by Aarsleff with a forest of precast concrete vertical and raking piles installed on four levels from the lowest basin level and up on the subsequent terraces to the top of the approximate 20m high level bank. The shortest piles, of about 6m, were installed at the lowest level and gradually increased in length to up to 26m at the top of the embankment. Piles over 15m long were jointed and all driven through the compacted rubble backfill to toe into the underlying sand. The required tension piles were installed to a preset level, whereas the piles to take compression were driven to a predetermined set. At each location of a main roof support stanchion a congested cluster of vertical and raking precast piles surrounded and complemented a radial line of 1m diameter bored piles previously installed by another contractor. Aarsleff had to report daily piling progress to Pol-Aqua and also conduct 33 static load tests and 140 dynamic tests, which were independently monitored and supervised by Poland’s Technical University of Wroclaw.

Aarsleff successfully completed its five-month contract early in March 2009 and a few days ahead of schedule. “Our success at the Warsaw Stadium has demonstrated that we are able to do mega jobs wherever in Europe as we can commit the necessary resources in a short time, which gives Aarsleff an advantage over competitors,” says Lars Rande. “We have done similar projects before, but this is one of the biggest and fastest and successfully completed in a very short time ahead of schedule. It’s easier in a decline to move rigs and other resources around, but even if we are all busy we have the flexibility in the group to move quickly as we have the common and important understanding of being able to help each other. In this case Poland had the benefit and maybe next time it could be Germany, Sweden, Denmark or UK. In the past we have had Danish rigs in UK, Polish rigs in Sweden, Germany and Denmark and German rigs several times in Poland. There is an exchange of equipment going on nearly all the time.”

 